Status of Port Connectivity Projects |
||||||||
---|---|---|---|---|---|---|---|---|
S. no. |
State |
Project Stretch |
Name of Port/ IWT Terminal Connected |
Length (km) |
Total Capital Cost (INR Cr.) |
Mode of Implementation (Tentative) |
Total Fund required (100% of TPC for EPC projects and 40% of TPC for HAM projects) |
Status |
1 |
Karnataka |
Road connectivity from Kasarkad side of Honnavar Port to NH |
Honnavar |
4 |
137 |
EPC |
137 |
IAC apprised the project in NHAI, approval pending with Ministry dt 31.05.21. |
2 |
Andhra Pradesh |
Anchorage Old Port Kakinada to Achampeta Junction |
Kakinada Port |
13.195 |
160.41 |
EPC |
160.41 |
IAC apprised the project in NHAI, approval pending with Ministry dt 25.05.21. |
3 |
Andhra Pradesh |
Port connectivty road (four lane) from East Break Water to Convent Junction |
Vishakhapatnam |
3.958 |
93.41 |
EPC |
93.41 |
IAC already apprised the Phase-I (3km). It has been decided now to include Phase-II. Proposal is under preparation. |
4 |
|
|
Total |
21 |
|
|
|
|